Ingérop South Africa was appointed by Lepelle Northern Water to provide professional services for the extensions of the existing (30 Ml/day) potable water treatment works at Olifantspoort to 65 Ml/day for the augmentation of water supply amongst others via the existing Olifants-Sand transfer scheme to the Greater Polokwane area. Ingérop South Africa, as leader of the professional civil, mechanical and electrical professional team, was responsible for the detail design, tender documentation, contract administration and construction supervision of the works that had two project time objectives. The first phase was for a plug flow delivery of water at the storage reservoirs in Polokwane by November 2009 and the second phase for the total augmented works were completed in June 2010.

Water

Client :
Lepelle Northern Water

Tags :
Ingerop, Water

Start Date : 2005
Handover : 2010